Lao Pride Forum
http://www.laopride.com/cgi-bin/yabb2/YaBB.cgi
General Category >> General Lao Board >> Laos to build 10 hydro-power dams over next 5 year
http://www.laopride.com/cgi-bin/yabb2/YaBB.cgi?num=1309357394

Message started by Lan Xang on 29th Jun, 2011 at 2:23pm

Title: Laos to build 10 hydro-power dams over next 5 year
Post by Lan Xang on 29th Jun, 2011 at 2:23pm
The 10-plant goal was set in the country's 7th National Socio-Economic Development Plan for 2011 to 2015, scheduled for approval by the National Assembly Friday, the Vientiane Times reported.

Of the 10, five are currently under construction. The Nam Ngum 5 in Vientiane province is 60 per cent complete, the Theun Hinboun expansion in Khammouane province is 78 per cent complete, the Nam Xong in Vientiane province is 30 per cent finished, the Nam Nhone in Luang Namtha is 91 per cent complete, and the Xekhaman 3 in Xekong province is 90 per cent complete, according to the plan awaiting the assembly's approval.

Laos already has 16 operational hydropower plants with a total capacity of 2,000 megawatts. The government has granted approval for feasibility studies on construction of 73 power plant projects over the past decade.

Some projects, such as the Xayaburi hydro-electric plant planned on the Mekong River, have run into regional opposition.

Cambodia, Thailand and Vietnam have called for delay of the dam's construction on the grounds that it could impact downstream fisheries and sedement flows. To date, only China has built dams on the Mekong River, the longest waterway in South-East Asia.

Hydroelectricity is the largest investment sector in Laos, having attracted 4 billion dollars over the past decade

The land-locked communist country, one of the world's poorest, earned 146 million dollars from exports of electricity to neighbouring Thailand during the first six months of the 2001/11 fiscal year, which started on October 1.

Title: Re: Laos to build 10 hydro-power dams over next 5 year
Post by Lan Xang on 29th Jun, 2011 at 2:24pm
Hydropower will generated a lot of revenue for the country. Laos is batter of ASEAN I agreed we need more dams.
;)

Title: Re: Laos to build 10 hydro-power dams over next 5 year
Post by Searching4TheRainbowInTheRose on 5th Jul, 2011 at 7:42pm
As long as the the misplaced locals where these dams are being built to be compensated nicely.

Title: Re: Laos to build 10 hydro-power dams over next 5 year
Post by LLXE on 5th Jul, 2011 at 9:03pm
Agreed. Locals should be compensated according to the market value for their land.
;)


PEACE wrote on 5th Jul, 2011 at 7:42pm:
As long as the the misplaced locals where these dams are being built to be compensated nicely.


Title: Re: Laos to build 10 hydro-power dams over next 5 year
Post by Searching4TheRainbowInTheRose on 6th Jul, 2011 at 9:22am
Not just compensations for displacement and/or land.  Jobs needed to be created as well for these folks. 

Title: Re: Laos to build 10 hydro-power dams over next 5 year
Post by LLXE on 7th Jul, 2011 at 10:10pm
I think they also used locals workforce to build road and hydropower.
http://www.youtube.com/watch?v=qxf_SBfLBlY

Title: Re: Laos to build 10 hydro-power dams over next 5 year
Post by Searching4TheRainbowInTheRose on 8th Jul, 2011 at 9:28am
Displacing these folks to another area that still requires self-sufficient living should be a short-term deal (not long-term as mentioned in the video).  Then these folks should migrate to the city to get jobs because there will be more job options for them.  With the overall planned schooling system and goals  coming up for the whole country,  these children should be able to benefit for better education, higher education and/or technical school opportunities. 

Title: Re: Laos to build 10 hydro-power dams over next 5 year
Post by LLXE on 8th Jul, 2011 at 10:08pm
Government should develop the area, school, hospital, manufacturing and created jobs for the villager. They have house and electricity but no jobs or enough land to farm.
;)

Title: Re: Laos to build 10 hydro-power dams over next 5 year
Post by WingsOfTomorrow on 9th Jul, 2011 at 12:14am
But these jobs have to be in the city (or near the vicinity of city) so they can support other business sectors as well.

Title: Re: Laos to build 10 hydro-power dams over next 5 year
Post by LLXE on 11th Jul, 2011 at 9:40am
Good point. Its all about location, ;) location.




PEACE wrote on 9th Jul, 2011 at 12:14am:
But these jobs have to be in the city (or near the vicinity of city) so they can support other business sectors as well.